2MW Combined Cooling, Heating, Power Plant

Client: MTN
Involvement: EPCM Contractor
End Date: July 2012
Value: R 50 Million

· Gas Generator plant supplying 1 x 2000 kWe on a
continuous basis.
· Gas supply train to Egoli Gas standards
· Heat exchangers
· Transfer pumps
· Medium Voltage system for grid tie purposes
· Electronic Control system
· Sound attenuation
· Absorption chiller to supply 1000 kWc on a continuous basis
· Low water usage cooling towers
· Make up water storage Water system
· Water treatment plant
· Redundant water transfer pump system
· Electrical motor control centre
· All associated building requirements
· Commissioning and testing