2MW combined cooling, heating, power plant

ISF Construction Services undertook the task of setting up a 2-megawatt combined cooling, heating and power plant for MTN as a Main Contractor. The team co-ordinated the implantation of a gas generator plant supplying 1 x 2000 kWc on a continuous basis. They also installed heat exchangers, and transfer pumps, as well as a medium voltage system for grid tie purposes.

The team also saw the installation of an electronic control system, sound attenuation, an absorption chiller to supply 1000 kWc on a continuous basis, low water usage cooling towers, a make-up water storage water system, a water treatment plant, a redundant water transfer pump system, an electrical motor control centre and all associated building requirements, including commissioning and testing.